First, I'm not sure where you got that Elio Motors did not have the Shreveport Plant until 1 May 2014, when
“Elio responded on Facebook just a bit short of an hour ago 04/11/2014: Yes, we have secured the plant in Shreveport, LA. “
So, do YOU believe it is 'realistic' for Elio Motors to BUILD & TEST 25-30 :"E" Series vehicles (with IAV engines), given the current state of their 'progress', and that Technosports Creative took 3-4 months to make the P4? If not, do you think it is still 'honest' for Elio Motors to keep saying they are "ON TRACK" to meet their 3rd Qtr 2015 projection? Keeping in mind that there has been a 4 Month delay in getting the cast engine parts 'machined' (possibly not even finished yet), and no word that the START of the prototypes has begun.
.